You booked a flat, the agreement for sale gave a date, and the date has gone. The RERA Act answers this directly, and it gives you a choice rather than a single remedy. Section 18 of the Real Estate (Regulation and Development) Act, 2016 is the section to read, and the rate you are owed is fixed by the Haryana rules, not by the builder. Both are published on the Haryana Real Estate Regulatory Authority's own website.

What the law actually says

Section 18(1) says that if the promoter fails to complete or is unable to give possession of an apartment, plot or building in accordance with the terms of the agreement for sale, or by the date specified in it, then on your demand he is liable to return the amount he received from you, with interest and with compensation, if you wish to withdraw from the project.

The same section's proviso covers the other choice. Where an allottee does not intend to withdraw from the project, the promoter must pay interest for every month of delay, until possession is handed over.

So the decision is yours and not the builder's: take your money back with interest, or stay in the project and be paid interest every month until you get the flat. Nothing in the agreement can take that choice away, because section 18 is the law and the agreement is below it.

What rate of interest

The Act says the rate is "as may be prescribed", and Haryana has prescribed it. Under the Haryana Real Estate (Regulation and Development) Rules, the rate of interest payable by the promoter to the allottee, or by the allottee to the promoter, is the State Bank of India highest marginal cost of lending rate plus two percent. The rules add that if that benchmark stops being used, it is replaced by whatever benchmark lending rate the State Bank of India fixes for lending to the general public.

Two things follow from that wording. The rate is the same in both directions, so the interest the builder owes you for being late is worked out the same way as the interest you would owe him for paying late. And it is not a figure in your builder-buyer agreement: a lower rate written into an agreement does not replace the prescribed one.

When the money has to reach you

The Haryana rules also fix the time. Any refund of money along with the applicable interest and compensation payable by the promoter under the Act or the rules must be paid to the allottee within ninety days from the date on which it becomes due.

Can the builder move the possession date

The date that matters is the one in your agreement for sale. A project's registration also carries a completion date, filed with the authority, and a promoter can apply to extend a registration. An extension of the registration is not the same thing as your agreement date moving, and section 18 is written against the agreement. Read your agreement for the date, the grace period if it gives one, and the force majeure clause, and compare that with the completion date on the RERA filing. On every project page here, the completion date filed with RERA is printed, so you can see the two side by side.

Defective title is separate

Section 18(2) deals with a different loss. If you suffer a loss because of defective title of the land the project is built on, the promoter must compensate you, and that claim is not barred by limitation under any other law. It is worth knowing it exists, because title problems surface years later.

What to do, in order

Put the demand in writing to the promoter, and keep proof of sending it: section 18 says he is liable "on demand". State which of the two you want, the refund with interest or the monthly interest, because they are different remedies. Attach the agreement for sale, the payment receipts and the registration number of the project. If the promoter does not answer, the complaint goes to the Authority that registered the project, which for a Gurugram project is HRERA Gurugram.

What this page does not do

This is a plain summary of what the Act and the Haryana rules say, read on 26 November 2026 at the Authority's own website. It is not legal advice, and it does not know your agreement. The clause that decides your case is in your own builder-buyer agreement, next to section 18. Read both before you write to anyone.

Where these facts come from

Read on 26 November 2026.

How this page is made. The facts are read from the RERA filings linked above and from the developers' own websites, on the date shown. The text is written with an AI model from those sources and published by Property Rahi.

Get the price list

Send on WhatsApp

This opens WhatsApp with your message filled in. Nothing is sent until you press send there, and this site does not store your number.