Two certificates decide whether a building you are buying into is finished in the eyes of the law, and they are not the same thing. The RERA Act defines both. One says the project was built to the sanctioned plan. The other says people may live in it. A buyer is usually shown neither, and should ask for both.
What the Act says each one is
Under the Real Estate (Regulation and Development) Act, 2016, a completion certificate means the completion certificate, or such other certificate by whatever name called, issued by the competent authority certifying that the real estate project has been developed according to the sanctioned plan, layout plan and specifications, as approved by the competent authority under the local laws.
An occupancy certificate means the occupancy certificate, or such other certificate by whatever name called, issued by the competent authority permitting occupation of any building, as provided under local laws, which has provision for civic infrastructure such as water, sanitation and electricity.
Read those two definitions next to each other and the difference is clear. The completion certificate is about the building matching the plan that was approved. The occupancy certificate is about the building being fit to live in, with water, sanitation and electricity actually provided for. In Haryana, for a licensed colony, the competent authority is the Town and Country Planning department, and people often call the occupancy certificate the occupation certificate or simply the OC.
Who issues it, and who must get it
The certificate is issued by the competent authority under the local laws, not by the builder and not by the RERA authority. It is the promoter's job to apply for it and obtain it. You do not apply for it yourself.
Why it matters when you take possession
The Act ties the handover to it. Section 17 provides that, in the absence of any local law, the promoter shall hand over the necessary documents and plans, including common areas, to the association of allottees or the competent authority, within thirty days after obtaining the occupancy certificate. So the occupancy certificate is the starting gun for the handover of the common areas, not an afterthought.
There is a second reason to care. Section 3(2)(b) of the Act says no registration is required where the promoter has received a completion certificate for a project before the Act commenced. A completion certificate is therefore the line at which a project leaves the RERA system. If someone tells you a project needs no RERA registration because it is complete, the certificate is the thing to ask to see.
What to ask for, and how to check it
Ask the promoter for a copy of the occupancy certificate for your tower or block, with its number and date, and for the completion certificate if one has been issued. Check three things on it: that it names the same licence and project as your agreement, that it covers your block or tower and not only part of the colony, and that its date is before the date you are being asked to take possession.
A certificate for a different phase of the same colony is not a certificate for yours. The Act's own explanation to section 3 says that where a project is developed in phases, every phase is a standalone project and must be registered separately. The same care applies to the certificates.
Possession without one
People do take possession of flats before an occupancy certificate is issued, and are then stuck: electricity and water connections that were meant to come through the builder, a registry that the sub-registrar may not accept, and a building that is legally not permitted to be occupied. Do not treat it as a formality that can follow later. Ask for the certificate before you pay the last instalment, not after.
On this site
Every project page here prints the completion date filed with RERA, the registration's validity and the licence with its own validity, which together tell you how far the project is from the stage where an occupancy certificate becomes possible. For a project that is years from completion, there is no certificate to ask for yet, and any claim that there is one deserves a second look.
What this page does not do
This is a plain summary of the definitions in the Act and the duty in section 17, read on 26 November 2026 at the Haryana Real Estate Regulatory Authority's website. It is not legal advice. Local rules decide the procedure in each state and the name the certificate is issued under.